3008 installs with Tricon main chassis, two additional 3008 main processors, triplicated I/O bus, TriStation application and SOE configuration in an engineered Tricon v9.6 and later controller configuration.
The commissioning workflow covers installed-hardware matching, controlled start-up and functional verification for this main processor module.
Important Notice: Confirm the complete 3008 marking, installed-system configuration, field connections and controlled functional test before commissioning or replacement.