Service work is performed at the selected IRB 4400 axis with the arm system secured, power and other energy isolated, and the matching axis connector documented. The replacement sequence covers sealing, motor-to-gear adjustment, fastener torque, oil restoration, calibration and a controlled test run.
Important Notice: Confirm 3HAC5954-1, IRB 4400 host, axis 2 or axis 3 position, Elmo hardware execution, pinion and gear condition, R3.MP2/R3.MP3 connector assignment, 24 VDC brake-release wiring, grounding, O-ring and flange sealing, motor adjustment, fastener torque, oil level, robot calibration and controlled test-run results before commissioning.
Apter Power 3HAC5954-1 Manuals and Guides
The first document is an Apter Power exact-part technical reference. The second opens the original ABB IRB 4400 product manual containing the axis 2 and axis 3 motor replacement, adjustment, calibration and test-run procedures.